+41%
+21%
+26%
+56%
+43%
+32%
Angular.js 4
Angular 4 is a web application framework. It provides a navigation toolbar, auto-complete, menus, and many more features.
Java 8
Applications on Java 8 show speed improvement without any specific work or tuning.
MongoDB
MongoDB has become popular with developers of all kinds who are building scalable applications using agile methodologies.
React
React is a JavaScript library that specializes in helping developers build user interfaces, or UIs.
Bootstrap
Bootstrap is the most popular CSS Framework for developing responsive and mobile-first websites.
Goal
The initial goal was to help airline partners worldwide provide their passengers with the best online experience. WorldTicket helps airlines optimize their direct sales channels and improve the user experience for the passenger.Main flow
Alexey Kolomoets
Artem Karpukhin
Alexander Palieshko
Vladimir Lazarchuk
Maria Grekova
Peek in and get more insights on how we work on each project: project discussion, whiteboard meetings, brainstorming, and simply gathering developers to make sure everything is going in the right direction.
As for the internal communication channels, Computools took into account WorldTicket’s preferences. To consolidate the communication flow, different tools for different tasks were preferred.
Skype was used for urgent inquiries and video calls, Slack was used for scheduling meetings and announcements between management, email was used for documentation and reports, and Jira was used to control progress and assign tasks.
As Scrum is most effective for teams working on complex projects, Computools agreed upon a project management methodology. It consisted of 2-4 week sprints. With each sprint, a team had to build the most important features first and come out with a potentially do-able idea. More features were built during the upcoming sprints and adjusted based on stakeholder and customer feedback.
CONSULTING
Product DESIGN
Product Engineering
1.
Launch
WorldTicket’s website was finished on time. Computools completed all the necessary testing to make sure the product had optimal performance and complied with the set standards and requirements.
2.
Transfer
Once all the tasks and formalities were completed, Computools hosted the site on their server via FTP and helped them configure it. In addition, the design was finalized by opening the site on Computools’s local host for testing.
3.
Education
Additional training materials and staff education was not required.
use link below to find
code sample